One thing is clear, MVP has been burying, and continues to bury, illegal, dangerous pipe. A study was done which proves that this is not debatable.
The people who are forced to live within MVP’s blast zone should not have to endure the daily stress of knowing it wasn’t built safely.
Bill McKibben hit the nail on the head when he
wrote that the “transition away from fossil fuels” language agreed to at COP28 could be either meaningful or meaningless depending on whether or not it is acted upon. This is similarly true for a rule written into the U.S. Code of Federal Regulations and published in the Federal Register, which is, or at least should be, a million times more legally binding than anything that came out of Dubai. That rule says that pipelines MUST be protected from external corrosion by having a protective coating which, among other things, is “sufficiently ductile to resist cracking.”
The rule exists because long sections of pipe flex a great deal between the time they are manufactured and coated at the plant and when they finally come to rest in a ditch. If the corrosion-proof coating on the pipe is not “sufficiently ductile” (flexible) to also flex when the pipe does, then it will crack. Once a crack in the coating opens up, it creates a pathway for moisture to come in contact with the steel and begin corroding the pipe.
Corrosion is a leading cause of pipeline explosions. Controlling corrosion is of particular concern regarding MVP because of its huge size (42-inch diameter) and the extremely high pressure (1,480 pounds per square inch, or psi,) it will be operating under.
In 2018 three-year-old Delaney Tercero was badly burned, as were her parents and younger sister, when a pipeline exploded near their home. Delaney died two days later after what must have been an agonizing ordeal in a hospital burn unit.
The pipeline that killed her exploded because of corrosion due to defective pipe coating. It was a 10-inch pipeline. MVP is a 42-inch pipeline. It also has defective pipe coating.
On January 30, 2024 there was a gas pipeline explosion in Oklahoma. It shot flames
500 feet into the air. The fire could be seen from 36 miles away, and it took hours to bring it under control. It started because of corrosion in an 8-inch pipeline and is thought to have migrated to a 24-inch pipeline based on the intensity of the fire. MVP is a 42-inch pipeline.
A 24-inch gas pipeline explosion in Oklahoma in January 2024 sends flames 500 feet into the air. MVP is a 42-inch pipeline.
In July 2023,
a gas pipeline exploded near Strasburg, Virginia, next to Interstate 81, shutting down traffic in both directions for hours. It was a 26-inch pipeline operating at 777 psi. MVP is a 42 inch pipeline that will operate at 1,480 psi.
Although language was inserted into last summer’s debt deal that allowed MVP to steamroll the normal permitting process, in no way did any of that language negate the “sufficiently ductile to resist cracking” rule, which has been on the books for
over 50 years. Even MVP’s own attorney said that the debt deal dealt specifically and only with permitting issues.
The key to understanding why MVP pipe is illegal lies in a study reported on in the Jan/Feb 2020 issue of
Corrosion Management (CM), a publication of the Institute of Corrosion. The article (on p. 16) is not very long nor is it difficult to understand, although there may be a word or two that requires googling. Everyone should read it and print a copy for future reference, before it becomes harder to access. To do so you might have to sign up for a free 30-day subscription to Scribd. The wording in the article and the results of the study make clear that MVP pipe coating has serious, unacceptable flaws.
It should be noted who undertook the study and wrote the article. It wasn’t anti-fossil fuel climate activists. Participants and contributors included TC Energy, the company that wanted to build the Keystone XL (KXL) pipeline, and Welspun, the company that manufactured and coated pipe for both KXL and MVP. One of the authors was James Ferguson, who worked for TC Energy (formerly Trans Canada) for over 18 years and who, at the time of the study, was the director of KXL Technical Services.
The point of the study was to determine how effective applying whitewash to KXL pipes was in terms of protecting the pipe coating from ultraviolet (UV) exposure, meaning the harmful effects of the sun. Most fossil fuel pipe, including KXL and MVP pipe, is coated with a greenish fusion bonded epoxy (FBE). FBE is, and is meant to be, flexible or ductile after it is applied and dries. However, exposure to the sun will reduce that flexibility over time and the coating can become brittle and crack. The National Association of Pipe Coating Applicators (NAPCA) recommends that FBE
not be exposed to the sun for more than six months.
The beginning of the
CM article has a paragraph with the heading “Effects of Ultraviolet Exposure on Fusion Bond Epoxy Coatings.” It says that “previous studies of exposed weathering of FBE coating had identified that UV exposure could have a serious deleterious effect on the inherent physical properties of the coating. This phenomenon is common to all FBE coatings that are primarily designed only for below ground service.” Over time, UV exposure will give the glossy green coating applied at the plant more of a chalky green look. Prolonged UV exposure will lead to “a noticeable reduction in the coating thickness” and cause all FBE coatings to “struggle to retain their original flexibility.” The change from glossy to chalky “clearly is accompanied by an embrittlement of the coating” and “reduction of flexibility performance.”
After KXL pipe was manufactured, the pipeline came up against all kinds of opposition for numerous very good reasons. And so it got delayed for years and was ultimately killed near the end of the Obama administration. Because TC Energy was aware of the problems UV creates for FBE coating, twice during that time period the company applied whitewash to the pipe to act as a sort of sunscreen. (It’s important to note here, and then remember, that whitewash was NOT applied to MVP pipe during the six to seven years it has sat in pipe yards and along the pipeline right of way. Dated satellite images can confirm this, as can photographs taken by frontline pipeline opponents.)
Regarding MVP, Buttigieg could rightly point to Sen. Joe Manchin (D-W.V.) as the reason it is being built. But it is on the secretary and a department under his control to make sure MVP is built safely and according to legal rules and regulations.
After former President Donald Trump was elected in 2016, Keystone XL came back to life, which is what prompted the study of its whitewashed pipe. They wanted to show that the whitewash had protected the FBE coating well enough that the pipe was still usable. But that’s not what they found.
The study tested three different groups of KXL pipe, which was generally stacked five layers high. One group included pipe below the top layer. Those pipes weren’t whitewashed, but they also were shaded from the sun by the pipe above them. The coating on those pipes tested OK.
The second group of pipe was from the top layer that had been whitewashed twice, once after 18-24 months of UV exposure and again four to five years later.
The third group involved the last few feet at the ends of top layer pipe. Those last few feet were not whitewashed so as not to cover up stenciling and markings. Those top layer pipe ends received no protection from the sun, and they best represent the coating on MVP pipe.
In eight out of ten tests, the whitewashed pipe failed to attain acceptable adhesion ratings. The non-whitewashed pipe ends “exhibited complete failures” regarding the adhesion test. In addition, the coating thickness on the non-whitewashed pipe ends had been reduced by more than 50%.
Another way to evaluate how well pipe coating will resist corrosion is to perform a catholic disbondment (CD) test. “The CD results of the non-whitewashed pipe ends exposed to UV were deemed total failures,” the study found.
“The flexibility tests were all deemed failures” on both the whitewashed and non-whitewashed pipe. All the flexibility tests “demonstrated similar results of cracking within the coating” even after they reduced the severity of the flexibility test three times from 2.5 degrees to 2.0 degrees to, finally, as little as 1.0 degree.
The first sentence under “Observations” states, “All non-whitewashed pipe that was exposed to continuous UV at the storage site” was “deemed no longer fit for purpose.” Even for whitewashed pipe, the flexibility of the underlying coating was “adversely affected to the point where it was no longer acceptable.”
In 2018 at an oil and gas forum in Canada, a KXL pipeline manager said that defective coating like this is
not something that can be remedied in the field but instead it requires shipping the pipe back to the plant for proper stripping, cleaning, and re-coating. This short video shows the elaborate process undertaken to properly apply FBE coating.
The slipshod method that MVP is applying to its degraded pipe coating is wholly inadequate. The “no longer fit for purpose” phrase in the
Corrosion Management article basically means that the pipe has a bad case of terminal skin cancer, which is not something MVP is going to remedy with its sporadic paintbrush-applied Band-Aids.
MVP’s band aid solution; the seven-year-old coating date, 2016, is barely visible.(Photo: POWHR/Mountain Valley Watch)
This coating problem is far from unique to MVP. Since 2010 the fossil fuel industry has built 70,000 miles of pipelines, and they have
plans to build another 70,000 miles. Most of those pipelines have been and will be fought against, resulting in pipe sitting above ground for extensive periods of time instead of getting quickly buried.
Right now pipeline giant Williams is building the
Regional Energy Access Expansion (REAE) project in Pennsylvania. It will lead to a significant increase in fracking in that state, which the majority of Pennsylvanians say they don’t want. Williams is also building the Louisiana Energy Gateway (LEG) project, which will increase gas flow to the LNG export terminals that the people living along the Gulf Coast are trying to shut down. Both REAE and LEG are being built with leftover pipe from the long dead Constitution Pipeline in New York. That pipe was manufactured and coated 10 years ago, and, like MVP pipe, its coating is shot.
But apparently and naturally, after sitting out in the sun for a decade, the pipe was cheap to buy. Cheap enough that it made economic sense for Williams to ship it all the way to Louisiana from New York. In fact, a Williams executive admitted that acquiring the
surplus pipe helped keep costs down, making those pipeline projects possible.
Secretary of Transportation Pete Buttigieg was recently in the news during the one-year anniversary of the train derailment in East Palestine, Ohio. He said
his department was doing all it could to prevent a similar disaster from happening again. He blamed Congress for not passing helpful legislation.
Regarding MVP, Buttigieg could rightly point to Sen. Joe Manchin (D-W.V.) as the reason it is being built. But it is on the secretary and a department under his control to make sure MVP is built safely and according to legal rules and regulations. That’s the whole reason that PHMSA, the Pipeline and Hazardous Materials Safety Administration, exists. It’s up to Buttigieg and PHMSA to enforce the “sufficiently ductile to resist cracking” rule. It’s up to them to publicly explain why they are disregarding the
Corrosion Management study. The fact that now, in his fourth year on the job, Buttigieg still has not even filled the top job at PHMSA makes one ask just how seriously is he regarding pipeline safety.
MVP would never get built near Manchin’s or Buttigieg’s homes. The people who are forced to live within MVP’s blast zone should not have to endure the daily stress of knowing it wasn’t built safely.
MVP and government regulators may argue that there are ways to detect corrosion and other problems before they cause harm. Yet the
biggest climate disaster of 2022 was caused by corrosion and created by the same company, Equitrans, that is building MVP. That huge methane leak occurred just 10 days after the site had been inspected and no problem was detected. It took almost two weeks for Equitrans to bring the leak under control.
In 2008 five people were injured and two homes were destroyed when a Williams gas pipeline exploded near Appomattox, Virginia. It was a 30-inch pipeline operating at about half the pressure MVP will operate at. The
cause of the explosion was external corrosion due to defective coating that had been compromised by rocks. An inspection undertaken shortly before the pipe exploded did not identify the corroded section of pipe.
MVP has a rock problem, too.(Photo: POWHR/Mountain Valley Watch)
The Pennsylvania attorney general has
charged Equitrans with crimes regarding a 2018 gas explosion that severely burned a four-year-old boy and his parents, killed their dog, and destroyed their home. The explosion resulted from a leaking Equitrans gas well that the company knew was leaking somewhere, but they never bothered to determine exactly where. Equitrans even had a protocol in place to help prevent corrosion at the well, but they didn’t follow it. One Equitrans employee testified that wells were often not serviced for budgetary reasons. And after the explosion, Equitrans didn’t even conduct the legally required investigation to determine the cause.
If Secretary Buttigieg and PHMSA are going to allow 42-inch MVP to come online with degraded pipe coating, they need to be asked, repeatedly, how they square that decision with the
Corrosion Management article and the KXL study. And if someday another person meets Delaney Tercero’s fate because of a MVP explosion, Buttigieg and regulators at PHMSA can blame Equitrans and Manchin… but the fault will be theirs too.