Aug 14, 2013
According to reporting by Reuters, the radioactive material within the fuel rods slated for removal are equivalent to 14,000 times the amount released in the atomic bombing of Hiroshima and the plan to move them "has never been attempted before on this scale."
The 400 tons of highly irradiated spent fuel and other nuclear materials will be taken from the crippled building and moved to a safer location, but the manner of the operation should be put in serious doubt, say the experts.
"They are going to have difficulty in removing a significant number of the rods," said Arnie Gundersen, a veteran U.S. nuclear engineer and director of Fairewinds Energy Education. The fuel rods are being stored in a cooling pool, but if a reaction begins, Gundersen expressed serious concern to Reuters about the company's ability to respond.
"To jump to the conclusion that it is going to work just fine," said Gundersen, "is quite a leap of logic."
"There is a risk of an inadvertent criticality if the bundles are distorted and get too close to each other," Gundersen continued.
"The problem with a fuel pool criticality is that you can't stop it. There are no control rods to control it," he said. "The spent fuel pool cooling system is designed only to remove decay heat, not heat from an ongoing nuclear reaction."
Reuters also quoted from a recent independent report which stated, a "full release from the Unit-4 spent fuel pool, without any containment or control, could cause by far the most serious radiological disaster to date."
The site's operator Tokyo Electric Power Company (TEPCO) has been mired in crisis ever since an earthquake and tsunami severely damaged the plant 2011. Most recently it was discovered that as much as 300 tons of "highly radioactive water" has been pouring into the Pacific Ocean on a daily basis from the plant, with no promising remedy offered by either the plant's owner TEPCO or the Japanese government.
_______________________
Join Us: News for people demanding a better world
Common Dreams is powered by optimists who believe in the power of informed and engaged citizens to ignite and enact change to make the world a better place. We're hundreds of thousands strong, but every single supporter makes the difference. Your contribution supports this bold media model—free, independent, and dedicated to reporting the facts every day. Stand with us in the fight for economic equality, social justice, human rights, and a more sustainable future. As a people-powered nonprofit news outlet, we cover the issues the corporate media never will. |
Our work is licensed under Creative Commons (CC BY-NC-ND 3.0). Feel free to republish and share widely.
Jacob Chamberlain
Jacob Chamberlain is a former staff writer for Common Dreams. His website is www.jacobpchamberlain.com.
According to reporting by Reuters, the radioactive material within the fuel rods slated for removal are equivalent to 14,000 times the amount released in the atomic bombing of Hiroshima and the plan to move them "has never been attempted before on this scale."
The 400 tons of highly irradiated spent fuel and other nuclear materials will be taken from the crippled building and moved to a safer location, but the manner of the operation should be put in serious doubt, say the experts.
"They are going to have difficulty in removing a significant number of the rods," said Arnie Gundersen, a veteran U.S. nuclear engineer and director of Fairewinds Energy Education. The fuel rods are being stored in a cooling pool, but if a reaction begins, Gundersen expressed serious concern to Reuters about the company's ability to respond.
"To jump to the conclusion that it is going to work just fine," said Gundersen, "is quite a leap of logic."
"There is a risk of an inadvertent criticality if the bundles are distorted and get too close to each other," Gundersen continued.
"The problem with a fuel pool criticality is that you can't stop it. There are no control rods to control it," he said. "The spent fuel pool cooling system is designed only to remove decay heat, not heat from an ongoing nuclear reaction."
Reuters also quoted from a recent independent report which stated, a "full release from the Unit-4 spent fuel pool, without any containment or control, could cause by far the most serious radiological disaster to date."
The site's operator Tokyo Electric Power Company (TEPCO) has been mired in crisis ever since an earthquake and tsunami severely damaged the plant 2011. Most recently it was discovered that as much as 300 tons of "highly radioactive water" has been pouring into the Pacific Ocean on a daily basis from the plant, with no promising remedy offered by either the plant's owner TEPCO or the Japanese government.
_______________________
Jacob Chamberlain
Jacob Chamberlain is a former staff writer for Common Dreams. His website is www.jacobpchamberlain.com.
According to reporting by Reuters, the radioactive material within the fuel rods slated for removal are equivalent to 14,000 times the amount released in the atomic bombing of Hiroshima and the plan to move them "has never been attempted before on this scale."
The 400 tons of highly irradiated spent fuel and other nuclear materials will be taken from the crippled building and moved to a safer location, but the manner of the operation should be put in serious doubt, say the experts.
"They are going to have difficulty in removing a significant number of the rods," said Arnie Gundersen, a veteran U.S. nuclear engineer and director of Fairewinds Energy Education. The fuel rods are being stored in a cooling pool, but if a reaction begins, Gundersen expressed serious concern to Reuters about the company's ability to respond.
"To jump to the conclusion that it is going to work just fine," said Gundersen, "is quite a leap of logic."
"There is a risk of an inadvertent criticality if the bundles are distorted and get too close to each other," Gundersen continued.
"The problem with a fuel pool criticality is that you can't stop it. There are no control rods to control it," he said. "The spent fuel pool cooling system is designed only to remove decay heat, not heat from an ongoing nuclear reaction."
Reuters also quoted from a recent independent report which stated, a "full release from the Unit-4 spent fuel pool, without any containment or control, could cause by far the most serious radiological disaster to date."
The site's operator Tokyo Electric Power Company (TEPCO) has been mired in crisis ever since an earthquake and tsunami severely damaged the plant 2011. Most recently it was discovered that as much as 300 tons of "highly radioactive water" has been pouring into the Pacific Ocean on a daily basis from the plant, with no promising remedy offered by either the plant's owner TEPCO or the Japanese government.
_______________________
We've had enough. The 1% own and operate the corporate media. They are doing everything they can to defend the status quo, squash dissent and protect the wealthy and the powerful. The Common Dreams media model is different. We cover the news that matters to the 99%. Our mission? To inform. To inspire. To ignite change for the common good. How? Nonprofit. Independent. Reader-supported. Free to read. Free to republish. Free to share. With no advertising. No paywalls. No selling of your data. Thousands of small donations fund our newsroom and allow us to continue publishing. Can you chip in? We can't do it without you. Thank you.