Britain's main safety regulator threw the government's energy plans into chaos tonight by damning the nuclear industry's leading designs for new plants. The Health and Safety Executive said it could not recommend plans for new reactors because of wide-ranging concerns about their safety.
The leading French and American reactors are central to plans for a nuclear renaissance aimed at keeping the lights on and helping to cut carbon emissions. The government needs to build a number of nuclear power stations in the next 10 years to replace old atomic and coal plants.
But the HSE has to approve the safety of the designs before they can be built. "We have identified a significant number of issues with the safety features of the design that would first have to be progressed. If these are not progressed satisfactorily then we would not issue a design acceptance confirmation," the agency concluded following a study of the latest French EPR and US AP1000 reactor designs.
Kevin Allars, director of new build at the HSE, admitted frustration that the design assessment process was already behind schedule owing to insufficient information from the companies promoting the reactors and a lack of enough trained staff in his own directorate.
The HSE's public report expresses "significant concerns" about the lack of separation between the safety protection and control systems on the EPR reactor design promoted by Areva and EDF of France. The safety body says another part of the reactor is "not entirely in alignment with international good practice".
The report says it has raised a number of issues with EDF and Areva relating to the structural integrity of the EPR and it concludes: "It is too early to say whether they can be resolved solely with additional safety case changes or whether they may result in design modifications being necessary."
The design put forward by Westinghouse, the American firm now owned by Toshiba of Japan, is also criticised, with the HSE saying the safety case on internal hazards has "significant shortfalls".
It criticizes the company for a "lack of detailed claims and arguments" to support various assertions, while questioning aspects of the civil and mechanical engineering plans as well as the structural integrity and "human factors".
It also complains that the reactor design was submitted in feet and inches rather than metric figures.
Industry experts said the HSE was in a pivotal position to make or break the government's wider plans because it could delay the planned reactors from coming on stream from 2017.
That is the time that ministers fear an "energy crunch" because most existing reactors will have been retired, many coal plants shut down and renewable power insufficiently advanced to take over.
John Large, a leading nuclear consultant, said: "The HSE as an independent agency will come under tremendous pressure to push through these designs. But if it stands up to [the] government and stops or delays these designs for two or three years until it is satisfied then developers could lose interest and we could fall behind in the queue of countries waiting to build nuclear."
Allars said he had not received any pressure so far from the government. While he had beefed up his staff and hoped to quicken the speed of his work, he insisted it was not his problem to worry ultimately about delays. "I am independent of government, and independent of industry and I will do what I need to protect society from any dangers of nuclear power. I will only be in a position to agree a generic design assessment if I get the right information [in future] to do that," he said.
The HSE said it might allow so-called exclusions over some of its concerns under which it would allow construction to proceed on the understanding that the problems would be addressed later.
Jean McSorley, consultant to Greenpeace's nuclear campaign, said it was highly likely reactor designs would not be ready for final sign-off at the end of the design process.
"This could leave the utilities and construction companies with real problems finishing projects, and that's very risky for them financially. Investment companies will also want to delay putting money into these projects until it is decided who takes responsibility for any potential cost overruns and delays," she said.
Areva shrugged off the concerns raised by the HSE. "It is important to emphasize that this is a normal part of what is a very transparent process and that it is entirely expected, as part of the design assessment process in the UK, for issues to be identified and resolved prior to licensing and construction," it said.
Dear Common Dreams reader, It’s been nearly 30 years since I co-founded Common Dreams with my late wife, Lina Newhouser. We had the radical notion that journalism should serve the public good, not corporate profits. It was clear to us from the outset what it would take to build such a project. No paid advertisements. No corporate sponsors. No millionaire publisher telling us what to think or do. Many people said we wouldn't last a year, but we proved those doubters wrong. Together with a tremendous team of journalists and dedicated staff, we built an independent media outlet free from the constraints of profits and corporate control. Our mission has always been simple: To inform. To inspire. To ignite change for the common good. Building Common Dreams was not easy. Our survival was never guaranteed. When you take on the most powerful forces—Wall Street greed, fossil fuel industry destruction, Big Tech lobbyists, and uber-rich oligarchs who have spent billions upon billions rigging the economy and democracy in their favor—the only bulwark you have is supporters who believe in your work. But here’s the urgent message from me today. It's never been this bad out there. And it's never been this hard to keep us going. At the very moment Common Dreams is most needed, the threats we face are intensifying. We need your support now more than ever. We don't accept corporate advertising and never will. We don't have a paywall because we don't think people should be blocked from critical news based on their ability to pay. Everything we do is funded by the donations of readers like you. When everyone does the little they can afford, we are strong. But if that support retreats or dries up, so do we. Will you donate now to make sure Common Dreams not only survives but thrives? —Craig Brown, Co-founder |
Britain's main safety regulator threw the government's energy plans into chaos tonight by damning the nuclear industry's leading designs for new plants. The Health and Safety Executive said it could not recommend plans for new reactors because of wide-ranging concerns about their safety.
The leading French and American reactors are central to plans for a nuclear renaissance aimed at keeping the lights on and helping to cut carbon emissions. The government needs to build a number of nuclear power stations in the next 10 years to replace old atomic and coal plants.
But the HSE has to approve the safety of the designs before they can be built. "We have identified a significant number of issues with the safety features of the design that would first have to be progressed. If these are not progressed satisfactorily then we would not issue a design acceptance confirmation," the agency concluded following a study of the latest French EPR and US AP1000 reactor designs.
Kevin Allars, director of new build at the HSE, admitted frustration that the design assessment process was already behind schedule owing to insufficient information from the companies promoting the reactors and a lack of enough trained staff in his own directorate.
The HSE's public report expresses "significant concerns" about the lack of separation between the safety protection and control systems on the EPR reactor design promoted by Areva and EDF of France. The safety body says another part of the reactor is "not entirely in alignment with international good practice".
The report says it has raised a number of issues with EDF and Areva relating to the structural integrity of the EPR and it concludes: "It is too early to say whether they can be resolved solely with additional safety case changes or whether they may result in design modifications being necessary."
The design put forward by Westinghouse, the American firm now owned by Toshiba of Japan, is also criticised, with the HSE saying the safety case on internal hazards has "significant shortfalls".
It criticizes the company for a "lack of detailed claims and arguments" to support various assertions, while questioning aspects of the civil and mechanical engineering plans as well as the structural integrity and "human factors".
It also complains that the reactor design was submitted in feet and inches rather than metric figures.
Industry experts said the HSE was in a pivotal position to make or break the government's wider plans because it could delay the planned reactors from coming on stream from 2017.
That is the time that ministers fear an "energy crunch" because most existing reactors will have been retired, many coal plants shut down and renewable power insufficiently advanced to take over.
John Large, a leading nuclear consultant, said: "The HSE as an independent agency will come under tremendous pressure to push through these designs. But if it stands up to [the] government and stops or delays these designs for two or three years until it is satisfied then developers could lose interest and we could fall behind in the queue of countries waiting to build nuclear."
Allars said he had not received any pressure so far from the government. While he had beefed up his staff and hoped to quicken the speed of his work, he insisted it was not his problem to worry ultimately about delays. "I am independent of government, and independent of industry and I will do what I need to protect society from any dangers of nuclear power. I will only be in a position to agree a generic design assessment if I get the right information [in future] to do that," he said.
The HSE said it might allow so-called exclusions over some of its concerns under which it would allow construction to proceed on the understanding that the problems would be addressed later.
Jean McSorley, consultant to Greenpeace's nuclear campaign, said it was highly likely reactor designs would not be ready for final sign-off at the end of the design process.
"This could leave the utilities and construction companies with real problems finishing projects, and that's very risky for them financially. Investment companies will also want to delay putting money into these projects until it is decided who takes responsibility for any potential cost overruns and delays," she said.
Areva shrugged off the concerns raised by the HSE. "It is important to emphasize that this is a normal part of what is a very transparent process and that it is entirely expected, as part of the design assessment process in the UK, for issues to be identified and resolved prior to licensing and construction," it said.
Britain's main safety regulator threw the government's energy plans into chaos tonight by damning the nuclear industry's leading designs for new plants. The Health and Safety Executive said it could not recommend plans for new reactors because of wide-ranging concerns about their safety.
The leading French and American reactors are central to plans for a nuclear renaissance aimed at keeping the lights on and helping to cut carbon emissions. The government needs to build a number of nuclear power stations in the next 10 years to replace old atomic and coal plants.
But the HSE has to approve the safety of the designs before they can be built. "We have identified a significant number of issues with the safety features of the design that would first have to be progressed. If these are not progressed satisfactorily then we would not issue a design acceptance confirmation," the agency concluded following a study of the latest French EPR and US AP1000 reactor designs.
Kevin Allars, director of new build at the HSE, admitted frustration that the design assessment process was already behind schedule owing to insufficient information from the companies promoting the reactors and a lack of enough trained staff in his own directorate.
The HSE's public report expresses "significant concerns" about the lack of separation between the safety protection and control systems on the EPR reactor design promoted by Areva and EDF of France. The safety body says another part of the reactor is "not entirely in alignment with international good practice".
The report says it has raised a number of issues with EDF and Areva relating to the structural integrity of the EPR and it concludes: "It is too early to say whether they can be resolved solely with additional safety case changes or whether they may result in design modifications being necessary."
The design put forward by Westinghouse, the American firm now owned by Toshiba of Japan, is also criticised, with the HSE saying the safety case on internal hazards has "significant shortfalls".
It criticizes the company for a "lack of detailed claims and arguments" to support various assertions, while questioning aspects of the civil and mechanical engineering plans as well as the structural integrity and "human factors".
It also complains that the reactor design was submitted in feet and inches rather than metric figures.
Industry experts said the HSE was in a pivotal position to make or break the government's wider plans because it could delay the planned reactors from coming on stream from 2017.
That is the time that ministers fear an "energy crunch" because most existing reactors will have been retired, many coal plants shut down and renewable power insufficiently advanced to take over.
John Large, a leading nuclear consultant, said: "The HSE as an independent agency will come under tremendous pressure to push through these designs. But if it stands up to [the] government and stops or delays these designs for two or three years until it is satisfied then developers could lose interest and we could fall behind in the queue of countries waiting to build nuclear."
Allars said he had not received any pressure so far from the government. While he had beefed up his staff and hoped to quicken the speed of his work, he insisted it was not his problem to worry ultimately about delays. "I am independent of government, and independent of industry and I will do what I need to protect society from any dangers of nuclear power. I will only be in a position to agree a generic design assessment if I get the right information [in future] to do that," he said.
The HSE said it might allow so-called exclusions over some of its concerns under which it would allow construction to proceed on the understanding that the problems would be addressed later.
Jean McSorley, consultant to Greenpeace's nuclear campaign, said it was highly likely reactor designs would not be ready for final sign-off at the end of the design process.
"This could leave the utilities and construction companies with real problems finishing projects, and that's very risky for them financially. Investment companies will also want to delay putting money into these projects until it is decided who takes responsibility for any potential cost overruns and delays," she said.
Areva shrugged off the concerns raised by the HSE. "It is important to emphasize that this is a normal part of what is a very transparent process and that it is entirely expected, as part of the design assessment process in the UK, for issues to be identified and resolved prior to licensing and construction," it said.